Production
Software for the Mailing Industry?
While
it is obvious that for a business to remain competitive
they must be adept at efficiently managing their resources
(people, materials, machines, etc.), most of the focus
on designing resource management\production software
has been to meet the direct needs of traditional manufacturing
concerns. Thus,
many of these system build upon the concept of a standard
Bill-Of-Material (BOM) that is planned, scheduled,
and resulting lower level components purchased and
received and tracked according to master schedule.
However,
for the Mailing Industry there really is no BOM nor
much in the way of inventory.
Each Job is a little different and the fundamental
unit for scheduling and tracking is the routing –
that is, which areas or workcenters the job needs
to go through, in what order, and how much time (machines
and labor) is required at each step?
For
example, in the simplest case, if an operation had
one workcenter to schedule, you wouldn’t need any
system at all.
You simply add in time for each job until it
you spilled over to next day.
A scheduling rule states, know as Johnson’s
Rule, states by scheduling the Jobs with the smallest
processing time first, you will have the best throughput
rate and average cycle time.
For example, in the above example, we have
two jobs finished in one day and one job finished
in 4 days. An
average of 1+1+4/3=2 days per job.
If we had scheduled Job 3 first, our average
would be 3+4+4/3 = almost 4 days per job.
The
reality of most mailing center operations prohibit
such a simple scheduling model to apply.
With several workcenters (inserting operations,
address file preparation, addressing
operations,
folding, parcel shipping, metering, incoming mail
sort, internal mail distribution) and a mix of labor
and machines working in parallel, combined with many
Jobs being estimated, and many jobs being scheduled,
each with different routing and process times, it
becomes nearly impossible to plan and schedule efficiently
without some computer assistance.
Furthermore,
There is a phenomenon called COVARIANCE that
explains why, most times, things just can’t get done
in the time you originally estimated. This theorem states that in a sequence of events, any deviations
that may occur will and will add up to maximum possible
delay. Workers
are late, material can’t be found, machine not calibrated,
etc. Without
explanation – things seem to come to a halt at times.
The
question is, what options does the Mailing Industry
have to work towards some of the promised benefits
production type of software?
The rest of this article summarizes the potential
benefits, risks, and requirements of implementing
a production software type system.
POTENTIAL
BENEFITS OF PRODUCTION SYSTEM
Just
some of the benefits of a successful system include:
Improved
customer service through
ability to estimate, track, and deliver Jobs on-time.
Direct
revenue increase through ability to run more jobs
through, in less time, by having a formal scheduling
system to identify exactly what resources are needed
(labor, machines) where, and when to achieve maximum
throughput.
The more jobs that can be run, in the same
time, with the same resources, obviously yields a
direct increase in revenue.
Improved
operational efficiency and direct cost savings by
planning and scheduling labor to minimize overtime
fluctuations, combining material purchases for volume
discounts, minimize inventory carrying costs, etc.
GETTING
STARTED
For
operations that are interested in pursuing these benefits,
it is crucial that they understand the level of commitment
that will be necessary to achieve reasonable success.
All too often, the pursuit of these benefits
is undertaken when there is crisis.
Too many late jobs, losing customers, un competitive
bids, soaring overhead costs, etc.
There
will be a series of reality checks on where the operation
is now, where you want to go, and do you have what
it takes to get there. For example, if you implement
a system that gives you a realistic schedule, and
the boss can continually interrupt the process to
rush a special order through for a close, key, customer,
then you better plan for that and make sure your system
can handle a mix of firm, standard jobs plus a percentage
of RUSH jobs.
As
another example, you will need some method of gathering,
estimating, and verifying standard process times. If you time the fastest worker, at their high of efficiency,
don’t expect an accurate schedule.
A
practical, working, realistic understanding of how
Jobs are processed and general flow of activity is
the first step in improving where you are.
This
information usually exists in some form, if only in
the manager’s head, to start with.
It is a good idea to establish agreement and
document with flow charts, procedures, time standards,
etc. If
you haven’t done this – you will find immediate opportunities
for improving your efficiencies during this phase.
IMPLEMENTATION
OPTIONS MATRIX
Now,
you are ready to investigate various system approaches.
You have basically three options with various
costs and risks as explained below.
SUMMARY
Be
sure to choose a system that offers a no-obligation
trial period, where you can enter in your own data
and see how it works for you.
Choose a vendor that is willing to work with
you, helping you set it up, enter your data, model
your facility.
Don’t make a decision based on a glossy brochure
and fancy dog-and-pony show.
Make a decision on the actual performance of
software, with a sample of your actual operational
data, before you cut the check.